Cafritz Foundation Art Center

Thursday, December 9, 2010

Progress Update

Confirmed with the client if they were going to purchase SIWS for all classrooms.
The stairwell widening took place over Thanksgiving week and had no impact to ITCO area.
The widening of the stairwell went well according to plans. There was no impact to ITOC.
Creating future meeting for the Information Technology design and equipment review for Infrastructure, telephones, media resources, cabling, and associated vendors.