The client has sent their power requirements for the IDF. This information was forwarded to facilities.
Scheduled an IT progress meeting for June 15th.
On site Wednesday to monitor plumbing worked performed around the ITOC and IT suite.
Review submittal for cable tray with cabling group.
Construction meeting scheduled for June 8th.
WDCE coordination meeting for security hardware setup for June 8th by facilities.
A walkthrough of the IDF with security vendor to review their work.
Review cable tray submittal for correct type. The size was too small requested that the IT cabling standards reflected the correct size.