Thursday, April 28, 2011

Progress Update

Reviewed estimated timeline with IT team, and construction schedule.
There has been no demolition work has of today. Submittals for the work are still being reviewed.
Hand off requisitions for the infrastructure and UPS facilities.
A client meeting was held on April 26th to review specification since the client request as changed. Some of the IT equipment is still be negotiated between and WDCE and facilities.
Received a drawing from the AV vendor for the design of the new projector. The design was forward to facilities.
Sent the client move to list to the client for confirmation.
Follow up with facilities on the cabling start timeline.
Monitor the construction work in the ITCO area.
Continue to monitor the helpdesk on the amount noise created with the construction.
A meeting has been setup for May 11th with the GC and cabling contractor to review IT standards.