Saturday, May 21, 2011

Progress Update

Attended the biweekly construction meeting.
Facilities working with contractor on submittals.
Met with cabling vendor to review the IT cabling standards and discuss any questions related to the project.
Performed a walkthrough with the GC, cabling vendor, NE , and college cabling group to review and confirm the work to be performed in the IDF. Some of the work in the IDF can be immediately.
Plumbing work to start the week of May 16th which involves the asset management area and maybe a portion of the operator area.
Still working with the client and facilities on IT equipment funding.
Perform site walkthroughs.
The plumbing work that started created serious vibrations from the jack hammering in the ITOC area had to be stopped and other alternatives for work had to done.