Cafritz Foundation Art Center

Tuesday, August 23, 2011

Progress Update

Site visit to WDCE.
Forward the new LCD quotes to the client.
Confirmed the power requirements for the IDF.
Working with facilities and architects for final approval of cutting the conduits in the classrooms since they run to the cable tray.
TP WDCE Next two weeks
Site walkthrough scheduled.
Construction meeting scheduled for August 24thth.
IT progress meeting scheduled for August 30th.
Update communication log, Blog, and timeline.