Site visit to WDCE.
Received quotes for SIWS and LCD’s. Working with media resource in preparing the requisitions.
GC working on IDF electrical power requirements for the project. The power for the servers in the IDF will be off for two days for some electrical work.
The large LCD’s in the large classroom will have the LCD’s at ADA height.
Constructions meeting Aug 24th.
IT progress update meeting Aug 30th.
WDCE meeting with facilities to review additional cabling work for one of the classrooms scheduled on Aug 24th.
Quotes for SIWS and the hallway LCD’s have been forward to facilities.
The cabling conduits and tray have been installed with the exception of the IDF.
The conduits for the AV in the classrooms are supposed to be cut which facilities and the GC is aware of.
The new request for 70” LCD has been forward to the client and the conduits and blocking have been done. Blocking is fine per AV group.
The LCD cost for the meeting room has been forward to client.
New IT request from the WDCE has been discussed for room 235 in making additional cabling and rack for the room. Facilities are aware of additional
Site walkthrough scheduled.
Follow up with facilities on the additional cabling for classroom
Follow up with the cabling group for quote from vendor.
Update communication log, Blog, and timeline.