•Site visit to WDCE.
•Cabling for voice and data complete.
•Client move scheduled for January 9th
•IT progress g/coordination/meeting scheduled for January 5th.
•AV implementation of SIWS is estimated to be completed by January 12th. The LCD to be completed at a later date in January.
•Asset management moved the clients on Jan9th.
•Waiting for Access Points to arrive for implementation.
•Proximity card readers are not ready. Key locks are on doors from the college until the vendor completes their configuration.
•Asset Management area to be cleaned from work on the second causing dust from the ceiling.
TP WDCE Next two weeks
Site walkthrough scheduled.
Follow up on client move.
Following up UPS fro NE group.
Confirm all AV is completed
IT progress meeting scheduled for end of January Date is TBA.